Staten Island Clean-Up and Safe-Up of Beaches and Parks (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install emergency chain link fencing, remove debris and sand, and demolish unsafe structures. This project will also include services of a bathymetric surveyor necessary for the opening of the swimmable beaches.

Project Timeline

Design

Start Date: November 2012
Completion Date: January 2013

Procurement

Start Date: January 2013
Projected Completion Date: October 2013
Completion Date: March 2013

Construction

Start Date: February 2013
Projected Completion Date: August 2013
Completion Date: July 2013

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 10/18/2019