NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Queens General Site Work (QG-713MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct pavements, fencing, plantings and general site work in Queens.

Project Timeline

Design

Start Date: January 2013
Projected Completion Date: March 2013
Completion Date: March 2014

Procurement

Start Date: March 2014
Projected Completion Date: December 2014
Completion Date: March 2015

Construction

Start Date: May 2015
Projected Completion Date: November 2016
Completion Date: November 2016

Understand how we build parks.

Funding

Total Funding: $646,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/20/2017

Was this information helpful?