NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Queens General Site Work (QG-513M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct pavements, handball courts, fencing, plantings and general site work in Queens.

Project Timeline

Design

Start Date: February 2013
Projected Completion Date: March 2013
Completion Date: April 2013

Procurement

Start Date: April 2013
Projected Completion Date: January 2014
Completion Date: June 2014

Construction

Start Date: August 2014
Projected Completion Date: February 2016
Completion Date: February 2016

Understand how we build parks.

Funding

Total Funding: $963,000
Funding Sources:
  • Mayoral
  • City Council

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/16/2017

Was this information helpful?