Queens General Site Work (QG-513M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct pavements, handball courts, fencing, plantings and general site work in Queens.

Project Timeline


Start Date: February 2013
Projected Completion Date: March 2013
Completion Date: April 2013


Start Date: April 2013
Projected Completion Date: January 2014
Completion Date: June 2014


Start Date: August 2014
Projected Completion Date: February 2016
Completion Date: February 2016

Understand how we build parks.


Total Funding: $850,000
Funding Sources:
  • Mayoral
  • City Council



Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project