Queens General Site Work (QG-613M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct play equipment, pavements, fencing, and plantings in Queens.

Project Timeline

Design

Start Date: January 2013
Projected Completion Date: March 2013
Completion Date: June 2014

Procurement

Start Date: June 2014
Projected Completion Date: March 2015
Completion Date: May 2015

Construction

Start Date: July 2015
Projected Completion Date: January 2017
Completion Date: November 2016

Understand how we build parks.

Funding

Total Funding: $1,546,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 12/15/2018