Rheingold Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    22% complete

This project will construct a new park with a tot lot and sitting area at the intersection of Bushwick Avenue and Beaver Street.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2012
Projected Completion Date: December 2015
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: November 2017
Completion Date: May 2018

Construction

Start Date: June 2018
Projected Completion Date: June 2019

Understand how we build parks.

Funding

Total Funding: $2,747,000
Funding Sources:
  • Mayoral
  • City Council

Location

Bushwick Avenue and Beaver Street

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/20/2018