Mathews-Palmer Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    66% complete

This project will reconstruct Mathews-Palmer Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2013
Projected Completion Date: September 2014
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: February 2017

Construction

Start Date: April 2017
Projected Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $2,468,000
Funding Source: City Council

Location

Matthews - Palmer Playground, Manhattan
West 45th Street between 9th and 10th Avenues, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 02/16/2018