Elizabeth H. Berger Plaza Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    28% complete

This project will construct Elizabeth H. Berger Plaza, closing the slip road between two smaller parks to create one larger plaza with plantings, a lawn mound, and seating.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2012
Projected Completion Date: September 2015
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: December 2018
Completion Date: April 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2020
Adjusted Completion Date: January 2021

Understand how we build parks.

Funding

Total Funding: $6,691,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council