Elizabeth H. Berger Plaza Park Construction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will construct a park at Elizabeth H. Berger Plaza.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: October 2012
Projected Completion Date: September 2015
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: December 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Trinity Place, Greenwich Street, Morris Street and Egdar Street