Elizabeth H. Berger Plaza Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    21% complete

This project will construct Elizabeth H. Berger Plaza, closing the slip road between two smaller parks to create one larger plaza with plantings, a lawn mound, and seating.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2012
Projected Completion Date: September 2015
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: December 2018
Completion Date: April 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2020

Understand how we build parks.

Funding

Total Funding: $6,691,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Trinity Place, Greenwich Street, Morris Street and Egdar Street

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 06/01/2020