John Allen Payne Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the play area to include new play equipment, swings, and spray shower area at John Allen Payne Playground

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: November 2014
Projected Completion Date: November 2015
Completion Date: April 2016

Procurement

Start Date: April 2016
Projected Completion Date: January 2017
Completion Date: February 2017

Construction

Start Date: April 2017
Projected Completion Date: April 2018
Completion Date: July 2018

Understand how we build parks.

Funding

Total Funding: $2,580,000
Funding Source: City Council

Location

John Allen Payne Playground , Brooklyn
3rd Avenue between 64th Street and 65th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/15/2018