Richmond Terrace Wetlands Streetscape Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    12% complete

This project will construct a seating area, overlook, paths, barrier rail, lighting and landscaping at the Richmond Terrace Wetlands.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2014
Projected Completion Date: June 2014
Completion Date: April 2016

Procurement

Start Date: April 2016
Projected Completion Date: January 2017
Completion Date: July 2017

Construction

Start Date: November 2017
Projected Completion Date: November 2019

Understand how we build parks.

Funding

Total Funding: $3,240,000
Funding Sources:
  • Mayoral
  • City Council

Location

Richmond Terrace Wetlands , Staten Island
Richmond Terrace between Van Name and Van Pelt Avenues, Staten Island

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 05/24/2018