Mary Whalen Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Mary Whalen Playground.

Project Timeline

Design

Start Date: March 2013
Projected Completion Date: August 2013
Completion Date: July 2014

Procurement

Start Date: July 2014
Projected Completion Date: April 2015
Completion Date: June 2015

Construction

Start Date: July 2015
Projected Completion Date: July 2016
Completion Date: May 2016