Project Timeline
Design
Start Date: March 2013
Projected Completion Date:
August 2013
Completion Date:
July 2014
Procurement
Start Date: July 2014
Projected Completion Date:
April 2015
Completion
Date:
June 2015
Construction
Start Date: July 2015
Projected Completion Date:
July 2016
Completion
Date:
May 2016