MacNeil Park Esplanade Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the esplanade in MacNeil Park.

Project Timeline

Design

Start Date: June 2013
Projected Completion Date: June 2015
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: November 2017

Construction

Start Date: February 2018
Projected Completion Date: August 2019
Completion Date: May 2019

Understand how we build parks.

Funding

Total Funding: $5,413,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Macneil Park , Queens
Poppenhusen Avenue, East River, 115th Street, College Place

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/16/2019