Flushing Meadows Corona Park Meadow Lake Promenade Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roadway and paths along Meadow Lake Promenade in Flushing Meadows Corona Park.

Project Timeline

Design

Start Date: February 2013
Projected Completion Date: September 2014
Completion Date: November 2015

Procurement

Start Date: November 2015
Projected Completion Date: August 2016
Completion Date: February 2017

Construction

Start Date: September 2017
Projected Completion Date: March 2019
Completion Date: April 2019

Understand how we build parks.

Funding

Total Funding: $4,366,000
Funding Sources:
  • Mayoral
  • City Council

Location

Flushing Meadows Corona Park , Queens
Between Boathouse Bridge and Ederle Terrace

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 07/17/2019