Baisley Pond Park Pathway Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct paths in Baisley Pond Park.
Project Timeline
Design
Start Date: May 2013
Projected Completion Date:
June 2014
Completion Date:
August 2014
Procurement
Start Date: August 2014
Projected Completion Date:
May 2015
Completion
Date:
April 2015
Construction
Start Date: May 2015
Projected Completion Date:
May 2016
Completion
Date:
May 2016
Understand how we build parks.
Funding
Funding Source: City Council
Location
Baisley Pond Park
, Queens
119th Avenue and Lake View Boulevard East to 155th Street and 122nd Avenue, Queens
Project Staff
Project Liaison: Joanne Amagrande
Contact NYC Parks
about this project
Last updated: 02/25/2021