Baisley Pond Park Pathway Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct paths in Baisley Pond Park.

Project Timeline

Design

Start Date: May 2013
Projected Completion Date: June 2014
Completion Date: August 2014

Procurement

Start Date: August 2014
Projected Completion Date: May 2015
Completion Date: April 2015

Construction

Start Date: May 2015
Projected Completion Date: May 2016
Completion Date: May 2016

Understand how we build parks.

Funding

Total Funding: $1,901,000
Funding Source: City Council

Location

Baisley Pond Park , Queens
119th Avenue and Lake View Boulevard East to 155th Street and 122nd Avenue, Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 02/25/2021