DeSalvio Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct DeSalvio Playground.

Project Timeline

Design

Start Date: October 2013
Projected Completion Date: June 2015
Completion Date: September 2015

Procurement

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: December 2016

Construction

Start Date: July 2017
Projected Completion Date: July 2018
Completion Date: February 2019

Understand how we build parks.

Funding

Total Funding: $1,718,000
Funding Sources:
  • Borough President
  • City Council

Location

DeSalvio Playground , Manhattan
Mulberry and Spring Streets

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project