Riverside Park South Natural Turf Ballfield & Greenway Reconstruction and Pier I Shade Structure Construction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the natural turf ballfield and greenway paths, and construct a shade structure on Pier I in Riverside Park South.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: March 2013
Projected Completion Date: October 2014
Adjusted Completion Date: August 2017

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Mayoral
  • City Council

Location

Riverside Park South , Manhattan
West 59th to West 72nd Streets in Riverside Park South, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 07/16/2018