Riverside Park South Natural Turf Ballfield & Greenway Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the natural turf ballfield and greenway paths in Riverside Park South.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: March 2013
Projected Completion Date: October 2014
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: August 2019
Adjusted Completion Date: December 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Mayoral
  • City Council

Location

Riverside Park South , Manhattan
Hudson River between West 59th Street and West 72nd Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/06/2019