NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Riverside Park South Natural Turf Ballfield & Greenway Reconstruction and Pier I Shade Structure Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the natural turf ballfield and greenway paths, and construct a shade structure on Pier I in Riverside Park South.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: March 2013
Projected Completion Date: October 2014
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: May 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Mayoral
  • City Council

Location

Riverside Park South , Manhattan
West 59th to West 72nd Streets in Riverside Park South, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 04/19/2018

Was this information helpful?