Hickman Playground and Harry Maze Playground Multipurpose Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the multi-purpose ballfields at Hickman Playground and Harry Maze Playground.

Project Timeline

Design

Start Date: September 2012
Projected Completion Date: February 2013
Completion Date: August 2014

Procurement

Start Date: August 2014
Projected Completion Date: May 2015
Completion Date: May 2015

Construction

Start Date: July 2015
Projected Completion Date: July 2016
Completion Date: August 2016

Understand how we build parks.

Funding

Total Funding: $2,115,000
Funding Sources:
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 08/20/2019