Wolfe's Pond Park Landscape Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the berm and restore the landscape in Wolfe's Pond Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: March 2013
Projected Completion Date: June 2014
Completion Date: October 2015

Procurement

Start Date: October 2015
Projected Completion Date: July 2016
Completion Date: June 2017

Construction

Start Date: October 2017
Projected Completion Date: September 2019
Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $3,808,000
Funding Sources:
  • Mayoral
  • State
  • Federal

Location

Wolfe's Pond Park , Staten Island
Holton Avenue and Purdy Place

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 12/12/2019