Asser Levy Playground Expansion

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will expand Asser Levy Playground into the roadbed of Asser Levy Place and construct a new artificial turf field and exercise track, new adult fitness equipment, benches, tables, drinking fountains, park lighting and trees.

Project Timeline

Design

Start Date: April 2012
Projected Completion Date: February 2013
Completion Date: May 2013

Procurement

Start Date: May 2013
Projected Completion Date: February 2014
Completion Date: September 2013

Construction

Start Date: October 2013
Projected Completion Date: October 2014
Completion Date: October 2014

Understand how we build parks.

Funding

Total Funding: $1,532,000
Funding Sources:
  • City Council
  • Private

Location

Asser Levy Playground , Manhattan
Asser Levy, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project