Wyckoff House Park Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct a comfort station in Wyckoff House Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: December 2017
Projected Completion Date: December 2018
Completion Date: January 2020

Procurement

Start Date: January 2020
Projected Completion Date: October 2020
Completion Date: January 2022

Construction

Start Date: April 2022
Projected Completion Date: October 2023

Understand how we build parks.

Funding

Total Funding: $6,835,000
Funding Sources:
  • Borough President
  • City Council

Location

Fidler-Wyckoff House Park , Brooklyn
Ralph Avenue, Ditmas Avenue and Clarendon Road.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 05/16/2022