Riverside Park Stairs and Sidewalk Reconstruction at Tiemann Place

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the stairs and adjacent perimeter sidewalk between Tiemann Place and Riverside Drive in Riverside Park.

Project Timeline

Design

Start Date: October 2011
Projected Completion Date: June 2013
Completion Date: October 2013

Procurement

Start Date: October 2013
Projected Completion Date: July 2014
Completion Date: June 2014

Construction

Start Date: July 2014
Projected Completion Date: July 2015
Completion Date: June 2015

Understand how we build parks.

Funding

Total Funding: $550,000
Funding Sources:
  • Borough President
  • City Council

Location

Riverside Park, Manhattan
Tiemann Place and Riverside Drive, Manhattan

 