Orchard Beach Pavilion Fencing, Netting, and Scaffolding Emergency Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install fencing, netting, and sidewalk bridge scaffolding at the Orchard Beach Pavilion.

Project Timeline

Design

Start Date: June 2012
Completion Date: September 2012

Procurement

Start Date: September 2012
Projected Completion Date: June 2013
Completion Date: October 2012

Construction

Start Date: June 2012
Projected Completion Date: September 2013
Completion Date: September 2013

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Pelham Bay Park , Bronx
Park Drive and Pelham Bay

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 08/11/2020