Highbridge Park Water Tower Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the water tower in Highbridge Park.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: July 2014
Projected Completion Date: March 2016
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: December 2018
Adjusted Completion Date: May 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • City Council

Location

Highbridge Park , Manhattan
West 173rd Street and Amsterdam Avenue, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/19/2019