Highbridge Park Water Tower Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    30% complete

This project will reconstruct the water tower in Highbridge Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: July 2014
Projected Completion Date: March 2016
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: December 2018
Completion Date: May 2019

Construction

Start Date: September 2019
Projected Completion Date: April 2021
Adjusted Completion Date: July 2021

Understand how we build parks.

Funding

Total Funding: $5,044,000
Funding Sources:
  • Mayoral
  • City Council

Location

Highbridge Park , Manhattan
West 173rd Street and Amsterdam Avenue

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/12/2020