Highbridge Park Water Tower Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    30% complete

This project will reconstruct the water tower in Highbridge Park.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: July 2014
Projected Completion Date: March 2016
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: December 2018
Completion Date: May 2019

Construction

Start Date: September 2019
Projected Completion Date: April 2021

Understand how we build parks.

Funding

Total Funding: $5,044,000
Funding Sources:
  • Mayoral
  • City Council

Location

Highbridge Park , Manhattan
West 173rd Street and Amsterdam Avenue

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 06/05/2020