NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Highbridge Park Water Tower Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the water tower in Highbridge Park.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: July 2014
Projected Completion Date: March 2016
Completion Date: April 2017

Procurement

Start Date: April 2017
Projected Completion Date: January 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • City Council

Location

Highbridge Park, Manhattan
West 173rd Street and Amsterdam Avenue, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 07/21/2017

Was this information helpful?