Sutton Place Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    15% complete

This project will reconstruct a portion of Sutton Place Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: April 2012
Projected Completion Date: September 2013
Completion Date: September 2015

Procurement

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: May 2017

Construction

Start Date: June 2017
Projected Completion Date: June 2018
Adjusted Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $1,465,000
Funding Sources:
  • City Council
  • Private

Location

Sutton Place Park , Manhattan
FDR Drive between 56th and 57th Streets

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 07/13/2018