Belt Parkway Landscape Restoration and Tree Planting at Canarsie

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    74% complete

This project will restore trees, preserve and re-establish the historic character of the parkway for drivers and pedestrians, enhance the visual cohesiveness of the parkway, and restore habitat along the Belt Parkway.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2014
Projected Completion Date: April 2015
Completion Date: May 2015

Procurement

Start Date: May 2015
Projected Completion Date: February 2016
Completion Date: March 2016

Construction

Start Date: September 2016
Projected Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $6,642,000
Funding Source: Mayoral

Location

Belt Parkway/Shore Parkway , Brooklyn
Belt Parkway at Paerdegat Basin Bridge, Rockaway Park Bridge and Fresh Creek Basin Bridge

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/16/2018