Project Timeline

Design

Start Date: April 2012
Projected Completion Date: January 2013
Completion Date: March 2013

Procurement

Start Date: March 2013
Projected Completion Date: December 2013
Completion Date: December 2013

Construction

Start Date: March 2014
Projected Completion Date: March 2015
Completion Date: July 2014