Roy Wilkins Recreation Center Kitchen and Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    79% complete

This project will reconstruct the kitchen, gymnasium roof, exterior waterproofing and site drainage at Roy Wilkins Recreation Center.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2011
Projected Completion Date: March 2014
Completion Date: April 2016

Procurement

Start Date: April 2016
Projected Completion Date: January 2017
Completion Date: November 2017

Construction

Start Date: March 2018
Projected Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $5,844,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Roy Wilkins Recreation Center , Queens
Baisley Boulevard and 177th Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project