Roy Wilkins Recreation Center Kitchen and Roof Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the kitchen, gymnasium roof, exterior waterproofing and site drainage at Roy Wilkins Recreation Center.
Project Timeline
Design
Start Date: June 2011
Projected Completion Date:
March 2014
Completion Date:
April 2016
Procurement
Start Date: April 2016
Projected Completion Date:
January 2017
Completion
Date:
November 2017
Construction
Start Date: March 2018
Projected Completion Date:
September 2019
Completion
Date:
August 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Roy Wilkins Recreation Center
, Queens
Baisley Boulevard and 177th Street
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 07/01/2022