Brooklyn Boiler & Heating Systems Reconstruction (BG-611M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct boilers and heating systems at various park facilities in Brooklyn.

Project Timeline

Design

Start Date: May 2011
Completion Date: September 2011

Procurement

Start Date: September 2011
Projected Completion Date: June 2012
Completion Date: July 2012

Construction

Start Date: October 2012
Projected Completion Date: October 2013
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $430,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 04/20/2021