Father Fagan Park Sitting Area Reconstruction and Charlton Plaza Water Service Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct the sitting area in Father Fagan Park and install water service at Charlton Plaza.

Project Timeline

Design

Start Date: March 2012
Projected Completion Date: March 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: February 2017

Construction

Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $1,550,000
Funding Source: City Council