Olmsted Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    68% complete

This project will reconstruct the Olmsted Center in Flushing Meadows Corona Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: April 2010
Projected Completion Date: August 2013
Completion Date: June 2014

Procurement

Start Date: June 2014
Projected Completion Date: March 2015
Completion Date: February 2015

Construction

Start Date: May 2015
Projected Completion Date: October 2016
Adjusted Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $29,650,000
Funding Source: Mayoral

Location

Flushing Meadows Corona Park , Queens
117-02 Roosevelt Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 07/05/2020