Olmsted Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    32% complete

This project will reconstruct the existing Olmsted Center in Flushing Meadows-Corona Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: April 2010
Projected Completion Date: August 2013
Completion Date: June 2014

Procurement

Start Date: June 2014
Projected Completion Date: March 2015
Completion Date: February 2015

Construction

Start Date: May 2015
Projected Completion Date: October 2016
Adjusted Completion Date: November 2018

Understand how we build parks.

Funding

Total Funding: $15,190,000
Funding Source: Mayoral

Location

Flushing Meadows Corona Park, Queens
117-02 Roosevelt Avenue, Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/16/2017