McCarren Park Pool & Bath House Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the pool and bathhouse at McCarren Park.

Project Timeline

Design

Start Date: July 2007
Projected Completion Date: November 2008
Completion Date: June 2009

Procurement

Start Date: June 2009
Projected Completion Date: March 2010
Completion Date: December 2009

Construction

Start Date: January 2010
Projected Completion Date: January 2012
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $31,434,000
Funding Sources:
  • Mayoral
  • City Council

Location

McCarren Park, Brooklyn
Lorimer Street between Bayard Street and Driggs Avenue

 

Project Staff

Project Liaison: Davey Ives