PFC Thomas Norton Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the comfort station at PFC Thomas Norton Park.

Project Timeline

Design

Start Date: July 2006
Completion Date: February 2010

Procurement

Start Date: February 2010
Projected Completion Date: October 2010
Completion Date: June 2011

Construction

Start Date: March 2012
Projected Completion Date: December 2012
Completion Date: November 2014

Understand how we build parks.

Funding

Total Funding: $759,000
Funding Source: City Council

Location

Pfc Norton Playground , Brooklyn
Nostrand Avenue between Kings Highway and Avenue P, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project