Williamsbridge Oval Recreation Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the recreation building at Williamsbridge Oval Park.
Project Timeline
Design
Start Date: May 2007
Projected Completion Date:
September 2007
Completion Date:
May 2008
Procurement
Start Date: May 2008
Projected Completion Date:
February 2009
Completion
Date:
August 2009
Construction
Start Date: April 2010
Projected Completion Date:
May 2011
Completion
Date:
November 2013