DiMattina Park, Dyker Beach Park, and Owl's Head Park Dog Run Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct separate dog runs for both small and large dogs in DiMattina Park, Dyker Beach Park and Owl's Head Park with new drainage, lighting, plantings, benches, paving, fencing, drinking fountains, and improved odor and dust control.

Project Timeline

Design

Start Date: July 2011
Projected Completion Date: June 2012
Completion Date: June 2013

Procurement

Start Date: June 2013
Projected Completion Date: March 2014
Completion Date: October 2013

Construction

Start Date: October 2013
Projected Completion Date: October 2014
Completion Date: March 2015

Understand how we build parks.

Funding

Total Funding: $1,427,000
Funding Sources:
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project