Andrew Haswell Green Searail and Rooftop Sitting Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a rooftop sitting area and searail in East River Esplanade.

Project Timeline

Design

Start Date: April 2008
Projected Completion Date: December 2012
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: September 2014
Completion Date: June 2015

Construction

Start Date: August 2015
Projected Completion Date: January 2017
Completion Date: January 2017

Understand how we build parks.

Funding

Total Funding: $4,668,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council
  • State

Location

Andrew Haswell Green Park , Manhattan
FDR Drive between East 60th Street and East 62nd Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/18/2019