Marcus Garvey Park Fire Watchtower Dismantling

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will dismantle the Marcus Garvey Park Fire Watchtower in preparation for its reconstruction.

Project Timeline

Design

Start Date: July 2013
Projected Completion Date: January 2014
Completion Date: June 2014

Procurement

Start Date: June 2014
Projected Completion Date: March 2015
Completion Date: November 2014

Construction

Start Date: August 2014
Projected Completion Date: February 2015
Completion Date: June 2015

Understand how we build parks.

Funding

Total Funding: $1,927,000
Funding Sources:
  • Borough President
  • City Council
  • Private

Location

Marcus Garvey Park, Manhattan
Marcus Garvey Park

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/20/2017