Battery Town Green and Battery Bikeway Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct lawns and bikeway at the Battery.
Project Timeline
Design
Start Date: December 2008
Projected Completion Date:
July 2010
Completion Date:
September 2011
Procurement
Start Date: September 2011
Projected Completion Date:
June 2012
Completion
Date:
July 2012
Construction
Start Date: September 2012
Projected Completion Date:
March 2014
Completion
Date:
October 2015
Understand how we build parks.
Funding
Funding Sources:
- State
- Federal
- Private
Location
The Battery
, Manhattan
State Street and Battery Place
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks