NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Battery Town Green and Battery Bikeway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

Project Timeline

Design

Start Date: December 2008
Projected Completion Date: July 2010
Completion Date: September 2011

Procurement

Start Date: September 2011
Projected Completion Date: June 2012
Completion Date: July 2012

Construction

Start Date: September 2012
Projected Completion Date: March 2014
Completion Date: October 2015

Understand how we build parks.

Funding

Total Funding: $12,000,000
Funding Sources:
  • State
  • Federal
  • Private

Location

The Battery, Manhattan
Battery Pl, State St and Whitehall St

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/20/2017

Was this information helpful?