Von King Cultural Arts Center Multipurpose Room Reconstruction
-
100% complete
-
100% complete
-
92% complete
This project will reconstruct the multipurpose room and fire alarm system at Von King Cultural Arts Center in Herbert Von King Park.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: September 2013
Projected Completion Date:
July 2014
Completion Date:
August 2016
Procurement
Start Date: August 2016
Projected Completion Date:
May 2017
Completion
Date:
June 2017
Construction
Start Date: September 2017
Projected Completion Date:
March 2019
Adjusted Completion
Date:
December 2021
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Herbert Von King Park
, Brooklyn
Tompkins Avenue, Marcy Avenue, Lafayette Avenue, Greene Avenue
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 07/01/2022