Von King Cultural Arts Center Multipurpose Room Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    82% complete

This project will reconstruct the multipurpose room and fire alarm system at Von King Cultural Arts Center in Herbert Von King Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: September 2013
Projected Completion Date: July 2014
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: May 2017
Completion Date: June 2017

Construction

Start Date: September 2017
Projected Completion Date: March 2019
Adjusted Completion Date: April 2020

Understand how we build parks.

Funding

Total Funding: $3,547,000
Funding Sources:
  • Mayoral
  • City Council

Location

Herbert Von King Park , Brooklyn
Tompkins Avenue, Marcy Avenue, Lafayette Avenue, Greene Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 04/19/2019