Von King Cultural Arts Center Multipurpose Room Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the multipurpose room in the Von King Cultural Arts Center in Herbert Von King Park.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: September 2013
Projected Completion Date: July 2014
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: May 2017
Completion Date: June 2017

Construction

Start Date: September 2017
Projected Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $3,547,000
Funding Sources:
  • Mayoral
  • City Council

Location

Herbert Von King Park, Brooklyn
Tompkins, Marcy, Lafayette and Greene Avenues, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/20/2017

Was this information helpful?