Von King Cultural Arts Center Multipurpose Room Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    84% complete

This project will reconstruct the multipurpose room and fire alarm system at Von King Cultural Arts Center in Herbert Von King Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: September 2013
Projected Completion Date: July 2014
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: May 2017
Completion Date: June 2017

Construction

Start Date: September 2017
Projected Completion Date: March 2019
Adjusted Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $6,517,000
Funding Sources:
  • Mayoral
  • City Council

Location

Herbert Von King Park , Brooklyn
Tompkins Avenue, Marcy Avenue, Lafayette Avenue, Greene Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/05/2020