Van Cortlandt Park Greenhouse Reconstruction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the greenhouse and head house at the Van Cortlandt Park Nursery.

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Start Date: June 2016
Projected Completion Date: October 2017
Adjusted Completion Date: December 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Van Cortlandt Park , Bronx
Between Van Cortlandt Park East and Major Deegan Expressway at East 242nd Street.

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/14/2018