Van Cortlandt Park Greenhouse Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the greenhouse and head house at the Van Cortlandt Park Nursery.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: June 2016
Projected Completion Date: October 2017
Completion Date: October 2020

Procurement

Start Date: October 2020
Projected Completion Date: July 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Van Cortlandt Park , Bronx
Between Van Cortlandt Park East and Major Deegan Expressway at East 242nd Street.

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 05/17/2021