Van Cortlandt Park Greenhouse Reconstruction
-
90% complete
-
0% complete
-
0% complete
This project will reconstruct the greenhouse and head house at the Van Cortlandt Park Nursery.
Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.
Project Timeline
Design
Start Date: June 2016
Projected Completion Date:
October 2017
Completion Date:
October 2020
Procurement
The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Van Cortlandt Park
, Bronx
Between Van Cortlandt Park East and Major Deegan Expressway at East 242nd Street.