Van Cortlandt Park Greenhouse Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the greenhouse and head house at the Van Cortlandt Park Nursery.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

We are currently soliciting bids for this project. If you are interested in submitting a bid on this project, you can find the documents on our Bid Solicitations page.

Project Timeline

Design

Start Date: June 2016
Projected Completion Date: October 2017
Completion Date: January 2019

Procurement

Start Date: January 2019
Projected Completion Date: October 2019
Adjusted Completion Date: August 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Van Cortlandt Park , Bronx
Between Van Cortlandt Park East and Major Deegan Expressway at East 242nd Street.

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/13/2019