44th Drive Pier Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the 44th Drive Pier and DEP sewer outfall located at 44th Drive in Queens.

Project Timeline

Design

Start Date: July 2008
Projected Completion Date: February 2013
Completion Date: July 2014

Procurement

Start Date: July 2014
Projected Completion Date: April 2015
Completion Date: July 2015

Construction

Start Date: September 2015
Projected Completion Date: March 2017
Completion Date: August 2016

Understand how we build parks.

Funding

Total Funding: $7,052,000
Funding Source: Mayoral

Location

East River and Vernon Boulevard, Queens

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/16/2017