Brooklyn and Staten Island Roofing Systems Reconstruction (CNYG-3109M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the roofing systems at various parks facilities in Brooklyn and Staten Island.
Project Timeline
Design
Start Date: December 2006
Completion Date:
March 2009
Procurement
Start Date: March 2009
Projected Completion Date:
December 2009
Completion
Date:
January 2010
Construction
Start Date: March 2010
Projected Completion Date:
February 2013
Completion
Date:
June 2014
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Brownsville Playground
, Brooklyn
Herman Avenue & Mother Gaston Boulevard -
Coney Island Beach & Boardwalk
, Brooklyn
Corbin Place to Coney Island Avenue -
CPL. Thompson Park
, Staten Island
Broadway, Henderso Avenue -
De Matti Park
, Staten Island
Tompkins Avenue, Chestnut Avenue -
Eleanor Roosevelt Playground
, Brooklyn
Dekalb Avenue / Kosciusko Street between Lewis & Stuyvesant Avenues -
Faber Pool and Park
, Staten Island
Richmond Terrace & Faber Street -
Franklin D. Roosevelt Boardwalk and Beach
, Staten Island
Natural Area and Boardwalk from Sand Lane to Vulcan Street, East of Father Capodanoo Boulevard -
Greenbelt Native Plant Center
, Staten Island
Victory Boulevard, Signs Road, Travis Avenue & Arthur Kill -
Luna Playground
, Brooklyn
West 12 Street & Surf Avenue -
Old Town Playground
, Staten Island
Parkinson Avenue, Kramer Street -
Pink Playground
, Brooklyn
Stanley Avenue & Eldert Lane -
Prospect Park
, Brooklyn
Prospect Park Southwest between Prospect Park West & 16 Street -
Rev. Dr. Maggie Howard Playground
, Staten Island
Tompkins Avenue & Broad Street -
Silver Lake Park
, Staten Island
Victory Boulevard, Clove Road, Forest Avenue
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/15/2021