Bronx and Queens Roofing Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct roofs at various park facilities in the Bronx and Queens.

Project Timeline

Design

Start Date: December 2006
Completion Date: March 2009

Procurement

Start Date: March 2009
Projected Completion Date: December 2009
Completion Date: September 2010

Construction

Start Date: October 2010
Projected Completion Date: October 2013
Completion Date: June 2015

Understand how we build parks.

Funding

Total Funding: $4,808,000
Funding Sources:
  • Mayoral
  • Borough President

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/20/2017