Brooklyn and Queens Recreation and Nature Centers HVAC Systems Reconstruction (CNYG-1910MA1)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct HVAC systems at Lost Battalion Hall Recreation Center and Brownsville Recreation Center.

Project Timeline

Design

Start Date: February 2010
Projected Completion Date: September 2013
Completion Date: January 2014

Procurement

Start Date: January 2014
Projected Completion Date: October 2014
Completion Date: August 2015

Construction

Start Date: November 2015
Projected Completion Date: October 2018
Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $619,000
Funding Sources:
  • Mayoral
  • Borough President

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/19/2019