Bronx and Manhattan Recreation and Nature Center HVAC Repair (CNYG-1810MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    45% complete

This multisite contract will reconstruct the HVAC systems for recreation centers and nature centers at parks locations in the Bronx and Manhattan.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: February 2010
Completion Date: November 2011

Procurement

Start Date: November 2011
Projected Completion Date: July 2012
Completion Date: February 2013

Construction

Start Date: April 2013
Projected Completion Date: March 2016
Adjusted Completion Date: December 2017

Understand how we build parks.

Funding

Total Funding: $450,000
Funding Sources:
  • Mayoral
  • City Council

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 12/14/2017