Citywide Pool Structural Systems Reconstruction (CNYG-1011M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct deteriorated structural systems at park and pool facilities citywide.

Project Timeline

Design

Start Date: January 2011
Completion Date: March 2011

Procurement

Start Date: March 2011
Projected Completion Date: November 2011
Completion Date: August 2013

Construction

Start Date: September 2013
Projected Completion Date: September 2016
Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: $2,332,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 07/19/2019