Citywide Deteriorated Plumbing Systems Reconstruction (CNYG-1711MA1)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct deteriorated plumbing systems at parks and recreation pool facilities citywide.

Project Timeline

Design

Start Date: March 2011
Completion Date: December 2011

Procurement

Start Date: December 2011
Projected Completion Date: September 2012
Completion Date: October 2012

Construction

Start Date: January 2013
Projected Completion Date: January 2014
Completion Date: June 2016

Understand how we build parks.

Funding

Total Funding: $919,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 12/14/2017