Citywide Reconstruction of Deteriorated Electrical Systems (CNYG-1611MA)

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    74% complete 

This multisite contract will reconstruct deteriorated electrical systems at parks and recreation pool facilities citywide.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2008
Completion Date: February 2011

Procurement

Start Date: February 2011
Projected Completion Date:November 2011
Completion Date: October 2012

Construction

Start Date: January 2013
Projected Completion Date:January 2014
Adjusted Completion Date: January 2017

Understand how we build parks.

Funding

Total Funding: $500,000
Funding Source:Mayor

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/13/2017