Van Cortlandt Park Putnam Greenway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    8% complete

This project will construct a portion of the Putnam Greenway in Van Cortlandt Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2008
Projected Completion Date: June 2016
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: April 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2020

Understand how we build parks.

Funding

Total Funding: $3,753,000
Funding Sources:
  • Mayoral
  • Federal

Location

Van Cortlandt Park , Bronx
City line to Van Cortlandt Park South

 

Project Staff

Contact NYC Parks about this project

Last updated: 12/13/2019