Van Cortlandt Park Putnam Greenway Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a portion of the Putnam Greenway in Van Cortlandt Park.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: May 2008
Projected Completion Date:
June 2016
Completion Date:
January 2018
Procurement
Start Date: January 2018
Projected Completion Date:
October 2018
Completion
Date:
April 2019
Construction
Start Date: August 2019
Projected Completion Date:
August 2020
Completion
Date:
October 2020
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
- Federal
Location
Van Cortlandt Park
, Bronx
City line to Van Cortlandt Park South
Project Staff
Contact NYC Parks about this projectLast updated: 02/26/2021