Van Cortlandt Park Putnam Greenway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    51% complete

This project will construct a portion of the Putnam Greenway in Van Cortlandt Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2008
Projected Completion Date: June 2016
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: April 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2020

Understand how we build parks.

Funding

Total Funding: $4,253,000
Funding Sources:
  • Mayoral
  • City Council
  • Federal

Location

Van Cortlandt Park , Bronx
City line to Van Cortlandt Park South

 

Project Staff

Contact NYC Parks about this project

Last updated: 07/02/2020