Van Cortlandt Park Putnam Greenway Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a portion of the Putnam Greenway in Van Cortlandt Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: May 2008
Projected Completion Date: June 2016
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: April 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $4,253,000
Funding Sources:
  • Mayoral
  • City Council
  • Federal

Location

Van Cortlandt Park , Bronx
City line to Van Cortlandt Park South

 

Project Staff

Contact NYC Parks about this project

Last updated: 12/02/2020