Soundview Park Running Track and Athletic Field Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the running track and athletic field in Soundview Park.

Project Timeline

Design

Start Date: June 2010
Projected Completion Date: November 2010
Completion Date: February 2011

Procurement

Start Date: February 2011
Projected Completion Date: October 2011
Completion Date: January 2012

Construction

Start Date: March 2012
Projected Completion Date: March 2013
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $5,154,000
Funding Source: Mayoral

Location

Soundview Park , Bronx
Metcalf Avenue and Seward Avenue

 

Project Staff

Project Liaison: Mike Ortiz