Soundview Park Playground and Court Reconstruction

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    95% complete 

This project will install new play equipment, swings, a spray shower area and open lawn as well as basketball and handball courts. New trees, shrubs and park lighting will further enhance the park experience.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: July 2007
Projected Completion Date:January 2012
Completion Date: February 2012

Procurement

Start Date: February 2012
Projected Completion Date:November 2012
Completion Date: March 2013

Construction

Start Date: May 2013
Projected Completion Date:October 2014
Adjusted Completion Date: January 2017

Understand how we build parks.

Funding

Total Funding: $3,645,000
Funding Sources:
  • Mayor
  • City Council

Location

Soundview Park, Bronx
Metcalf Avenue and Seward Avenue in Soundview Park

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 01/13/2017