Bronx General Site Work (XG-112M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct play equipment, safety surfacing, handball courts, basketball courts, pavements, fencing, plantings and general site work in the Bronx.

Project Timeline

Design

Start Date: July 2011
Completion Date: October 2011

Procurement

Start Date: October 2011
Projected Completion Date: July 2012
Completion Date: June 2012

Construction

Start Date: March 2013
Projected Completion Date: March 2015
Completion Date: March 2016

Understand how we build parks.

Funding

Total Funding: $2,438,000
Funding Source: Mayoral